Probability distribution fitting of schedule overruns in construction projects

P. E.D. Love, C. P. Sing, X. Wang, D. J. Edwards, H. Odeyinka

Research output: Contribution to journalArticlepeer-review

28 Citations (Scopus)

Abstract

The probability of schedule overruns for construction and engineering projects can be ascertained using a 'best fit' probability distribution from an empirical distribution. The statistical characteristics of schedule overruns occurring in 276 Australian construction and engineering projects were analysed. Skewness and kurtosis values revealed that schedule overruns are non-Gaussian. Theoretical probability distributions were then fitted to the schedule overrun data; including the Kolmogorov-Smirnov, Anderson-Darling and Chi-Squared non-parametric tests to determine the 'Goodness of Fit'. A Four Parameter Burr probability function best described the behaviour of schedule overruns, provided the best overall distribution fit and was used to calculate the probability of a schedule overrun being experienced. The statistical characteristics of contract size and schedule overruns were also analysed, and the Wakeby (<AU$1 m and AU$11-50 m), Three Parameter Log-logistic (AU$1-A$10 m) and Beta (AU$51-A$100 m and >AU$101 m) models provided the best distribution fits and were used to calculate schedule overrun probabilities by contract size.

Original languageEnglish
Pages (from-to)1231-1247
Number of pages17
JournalJournal of the Operational Research Society
Volume64
Issue number8
DOIs
Publication statusPublished - Aug 2013
Externally publishedYes

Keywords

  • Australia
  • distribution fitting
  • probability
  • probability distribution
  • schedule overrun

ASJC Scopus subject areas

  • Management Information Systems
  • Strategy and Management
  • Management Science and Operations Research
  • Marketing

Fingerprint

Dive into the research topics of 'Probability distribution fitting of schedule overruns in construction projects'. Together they form a unique fingerprint.

Cite this