TY - JOUR
T1 - Insurable and non-insurable risks in complex project deals
T2 - case of the Ghanaian construction industry
AU - Owusu-Manu, De Graft
AU - Ghansah, Frank Ato
AU - Darko, Amos
AU - Asiedu, Richard Ohene
AU - Edwards, David John
N1 - Publisher Copyright:
© 2020, Emerald Publishing Limited.
PY - 2020/10/28
Y1 - 2020/10/28
N2 - Purpose: The purpose of this study is to investigate the insurable risks that impacted the operations on complex construction projects in developing countries using Ghana as a case study. Design/methodology/approach: In this study, structured questionnaires were used to collect relevant information from the top management of construction and insurance firms in Ghana, comprising 50 industry professionals. The study adopted the χ2 and independent samples’ t test to interpret the responses from participants. Findings: The study revealed the major risks that severely impacted the operations on complex construction projects, including strikes and labour disputes, long waiting time for approval of test samples, damages to property during construction, delay in payment to contractor for work done, poor construction method, pressure to deliver project on an accelerated schedule, labour shortage, permits delayed or take longer than expected, inaccurate materials estimating, change in weather pattern, low productivity of subcontractors and inadequate contractor experience. Practical implications: The study is expected to contribute to increase in the awareness of the insurable risks and policies that project participants are exposed to, which will serve as a decision-making tool for contract formation. Originality/value: This study assists in managing construction and insurance firms to note the major risk in managing a complex construction project. In addition to knowing the major risks identified, the study investigates the insurable risk by managing both construction and insurance firms.
AB - Purpose: The purpose of this study is to investigate the insurable risks that impacted the operations on complex construction projects in developing countries using Ghana as a case study. Design/methodology/approach: In this study, structured questionnaires were used to collect relevant information from the top management of construction and insurance firms in Ghana, comprising 50 industry professionals. The study adopted the χ2 and independent samples’ t test to interpret the responses from participants. Findings: The study revealed the major risks that severely impacted the operations on complex construction projects, including strikes and labour disputes, long waiting time for approval of test samples, damages to property during construction, delay in payment to contractor for work done, poor construction method, pressure to deliver project on an accelerated schedule, labour shortage, permits delayed or take longer than expected, inaccurate materials estimating, change in weather pattern, low productivity of subcontractors and inadequate contractor experience. Practical implications: The study is expected to contribute to increase in the awareness of the insurable risks and policies that project participants are exposed to, which will serve as a decision-making tool for contract formation. Originality/value: This study assists in managing construction and insurance firms to note the major risk in managing a complex construction project. In addition to knowing the major risks identified, the study investigates the insurable risk by managing both construction and insurance firms.
KW - Complex construction project
KW - Ghana
KW - Insurable risk
KW - Non-insurable risk
KW - Risk management
KW - construction industry
UR - http://www.scopus.com/inward/record.url?scp=85085076850&partnerID=8YFLogxK
U2 - 10.1108/JEDT-10-2019-0265
DO - 10.1108/JEDT-10-2019-0265
M3 - Article
AN - SCOPUS:85085076850
SN - 1726-0531
VL - 18
SP - 1971
EP - 1995
JO - Journal of Engineering, Design and Technology
JF - Journal of Engineering, Design and Technology
IS - 6
ER -